Two major infrastructure projects on North 9th Street in Cañon City have reached substantial completion, marking the end of a construction effort that brought new pavement, water lines, stormwater infrastructure and accessibility upgrades to the corridor.

The City announced the 2026 completion update on November 12, 2026. Together, the projects covered approximately 1.32 miles of North 9th Street between Mystic Avenue and Washington Street and carried a combined construction cost of approximately $7.2 million.

What changed along North 9th Street

The work included a broad reconstruction of the roadway and underground systems. Crews installed 34,750 square yards of new asphalt pavement and built 7,636 linear feet of new or replacement curb and gutter.

The project also added 1,400 square yards of concrete paving for driveways and approaches. Thirty-four Americans with Disabilities Act pedestrian ramps were installed or upgraded, improving access along the route.

At the intersection of 9th Street and Mystic Avenue, the Hydraulic Ditch box culvert was completely reconstructed. The work addressed a major piece of drainage infrastructure at the southern end of the project area.

Water and stormwater work

A substantial part of the investment went below the street. The City replaced 3,830 linear feet of existing water main and 48 water service lines.

Improvements were also coordinated with the Orchard Park and Park Center districts. According to the City, that work was intended to improve delivery, remove infrastructure conflicts and reduce future risks for the districts and their customers.

Drainage improvements included 1,830 linear feet of new storm sewer and 10 stormwater inlets. The additions were designed to improve stormwater management throughout the North 9th Street corridor.

City thanks residents and utility partners

The City thanked schools, residents, businesses and the broader public for their patience, cooperation and understanding during construction. The work affected a corridor used by nearby schools, local businesses and residents over the course of the project.

Several utility providers worked alongside the City to upgrade or relocate existing infrastructure during construction. Those partners included Atmos Energy, Black Hills Energy, Lumen Technologies, Spectrum, Segra Communications, Fremont Sanitation, Hydraulic Ditch Company, Fruitland Ditch Company, Orchard Park Water District, Park Center Water District and Visionary Broadband.

The completion announcement represents the current project milestone provided by the City. The source does not specify whether additional minor work, inspections or closeout activity remains after substantial completion.